Shorter Reads

Croudace Homes Ltd v PRB Wiring Solutions Ltd: Timing important when challenging adjudicator’s fees

Alexander Jullienne in our Construction team gives his thoughts on Croudace Homes Ltd v PRB Wiring Solutions Ltd, a recent case in which the TCC enforced an adjudicator’s decision requiring the defendant to pay the adjudicator’s fees and expenses.

1 minute read

Published 12 August 2020

Share

Key information

The TCC has confirmed in Croudace Homes Ltd v PRB Wiring Solutions Ltd  [2020] EWHC 2139 (TCC) that a party intending to challenge the reasonableness of an adjudicator’s fees, should take effective action to do so and in any event prior to payment, otherwise it will lose its right to challenge.

The claimant (Croudace) was successful in an adjudication against the defendant (PRB) that it was entitled to terminate its contract with PRB in respect of a project at Tetsworth, Mount Hill Farm and would not be liable for loss and damage arising from the termination. The Adjudicator decided that PRB was liable for 100% of his fees and expenses and directed that Croudace pay his fees and expenses in the first instance, and then reclaim the sum back from PRB.

Croudace paid the Adjudicator’s fees, however, PRB refused to reimburse Croudace for those fees. Croudace subsequently commenced adjudication enforcement proceedings against PRB seeking reimbursement of the Adjudicator’s fees.

Although PRB accepted liability to reimburse the fees paid to the Adjudicator it sought to challenge the quantification of those fees.

In dismissing PRB’s challenge, Mr Nissen QC concluded that it was not open to PRB to challenge the fees because no effective action had been taken to challenge the reasonableness of the adjudicator’s fees at the appropriate juncture. Mr Nissen QC confirmed that in the absence of any evidence of a challenge to the reasonableness of the fees of the Adjudicator before Croudace had paid them, it was “simply too late and inappropriate” to raise issues as to quantum when it had already been paid.

Further, Mr Nissen QC said that in any event, PRB’s challenge to the reasonableness of the fees by relying on the quantum of fees incurred by a different adjudicator presiding over a similarly contested adjudication, would not have succeeded. Mr Nissen QC remarked that in adjudication, the adjudicator’s costs can vary considerably and that there was no reason to suppose that different adjudicators will charge the same amount for performing the same adjudication let alone a different adjudication.

Whilst Croudace ultimately obtained judgment together with an order for indemnity costs, it was undeniably inconvenienced by PRB’s approach. Such inconvenience may not have arisen had the Adjudicator directed that PRB pay the Adjudicator direct instead of involving Croudace in the payment process. Whilst this would have prevented Croudace from having to issue enforcement proceedings, most adjudications contain terms and conditions to the effect that the parties will be jointly and severally liable for the adjudicator’s fees and disbursements meaning they might have been dragged into the proceedings in any event. One takeaway is that parties should at the outset look to agree on how the adjudicator’s fees will be paid if they are successful/unsuccessful in an attempt to avoid similar situations such as those faced by Croudace in future adjudications.

 

Arrow Back to Insights

Shorter Reads

Croudace Homes Ltd v PRB Wiring Solutions Ltd: Timing important when challenging adjudicator’s fees

Alexander Jullienne in our Construction team gives his thoughts on Croudace Homes Ltd v PRB Wiring Solutions Ltd, a recent case in which the TCC enforced an adjudicator’s decision requiring the defendant to pay the adjudicator’s fees and expenses.

Published 12 August 2020

The TCC has confirmed in Croudace Homes Ltd v PRB Wiring Solutions Ltd  [2020] EWHC 2139 (TCC) that a party intending to challenge the reasonableness of an adjudicator’s fees, should take effective action to do so and in any event prior to payment, otherwise it will lose its right to challenge.

The claimant (Croudace) was successful in an adjudication against the defendant (PRB) that it was entitled to terminate its contract with PRB in respect of a project at Tetsworth, Mount Hill Farm and would not be liable for loss and damage arising from the termination. The Adjudicator decided that PRB was liable for 100% of his fees and expenses and directed that Croudace pay his fees and expenses in the first instance, and then reclaim the sum back from PRB.

Croudace paid the Adjudicator’s fees, however, PRB refused to reimburse Croudace for those fees. Croudace subsequently commenced adjudication enforcement proceedings against PRB seeking reimbursement of the Adjudicator’s fees.

Although PRB accepted liability to reimburse the fees paid to the Adjudicator it sought to challenge the quantification of those fees.

In dismissing PRB’s challenge, Mr Nissen QC concluded that it was not open to PRB to challenge the fees because no effective action had been taken to challenge the reasonableness of the adjudicator’s fees at the appropriate juncture. Mr Nissen QC confirmed that in the absence of any evidence of a challenge to the reasonableness of the fees of the Adjudicator before Croudace had paid them, it was “simply too late and inappropriate” to raise issues as to quantum when it had already been paid.

Further, Mr Nissen QC said that in any event, PRB’s challenge to the reasonableness of the fees by relying on the quantum of fees incurred by a different adjudicator presiding over a similarly contested adjudication, would not have succeeded. Mr Nissen QC remarked that in adjudication, the adjudicator’s costs can vary considerably and that there was no reason to suppose that different adjudicators will charge the same amount for performing the same adjudication let alone a different adjudication.

Whilst Croudace ultimately obtained judgment together with an order for indemnity costs, it was undeniably inconvenienced by PRB’s approach. Such inconvenience may not have arisen had the Adjudicator directed that PRB pay the Adjudicator direct instead of involving Croudace in the payment process. Whilst this would have prevented Croudace from having to issue enforcement proceedings, most adjudications contain terms and conditions to the effect that the parties will be jointly and severally liable for the adjudicator’s fees and disbursements meaning they might have been dragged into the proceedings in any event. One takeaway is that parties should at the outset look to agree on how the adjudicator’s fees will be paid if they are successful/unsuccessful in an attempt to avoid similar situations such as those faced by Croudace in future adjudications.

 

Need some more information? Make an enquiry below.

    Subscribe

    Please add your details and your areas of interest below

    Specialist sectors:

    Legal services:

    Other information:

    Jurisdictions of interest to you (other than UK):



    Enjoy reading our articles? why not subscribe to notifications so you’ll never miss one?

    Subscribe to our articles

    Message us on WhatsApp (calling not available)

    Please note that Collyer Bristow provides this service during office hours for general information and enquiries only and that no legal or other professional advice will be provided over the WhatsApp platform. Please also note that if you choose to use this platform your personal data is likely to be processed outside the UK and EEA, including in the US. Appropriate legal or other professional opinion should be taken before taking or omitting to take any action in respect of any specific problem. Collyer Bristow LLP accepts no liability for any loss or damage which may arise from reliance on information provided. All information will be deleted immediately upon completion of a conversation.

    I accept Close

    Close
    Scroll up
    ExpandNeed some help?Toggle

    < Back to menu

    I have an issue and need your help

    Scroll to see our A-Z list of expertise

    Get in touch

    Get in touch using our form below.



      Business Close
      Private Wealth Close
      Hot Topics Close